| Event status | Message ID | Publication date/time | Market participant | Affected asset or unit | Type of unavailability | Event start | Event stop | Unavailable capacity | Fuel type |
| Active | JW2 4-07-202601161918-001_003 |
2026-01-18
09:03:01
|
TAURON Wytwarzanie S.A. | Power plant Nowe Jaworzno, Unit 910 MW | Unplanned |
2026-01-16
19:57:00
|
2026-01-19
18:00:00
|
834 MW | Fossil Hard coal |
| Active | JW3 2-06-202601141313-004_001 |
2026-01-14
13:13:01
|
TAURON Wytwarzanie S.A. | Power plant Jaworzno III, Unit 6 | Planned |
2026-01-17
00:01:00
|
2026-01-24
00:00:00
|
211 MW | Fossil Hard coal |
| Active | LZA31-10-202406200758-001_008 |
2025-12-17
12:37:37
|
TAURON Wytwarzanie S.A. | Power plant Łaziska, Unit 10 | Planned |
2026-01-01
00:01:00
|
2026-04-17
00:00:00
|
211 MW | Fossil Hard coal |
| Active | JW3 2-02-202307181208-002_006 |
2025-04-29
12:08:00
|
TAURON Wytwarzanie S.A. | Power plant Jaworzno III, Unit 2 | Planned |
2026-01-02
00:00:00
|
2026-04-02
00:00:00
|
210 MW | Fossil Hard coal |
| Active | JW3 1-03-202309220648-001_008 |
2025-04-18
08:38:00
|
TAURON Wytwarzanie S.A. | Power plant Jaworzno III, Unit 3 | Planned |
2025-12-01
00:01:00
|
2026-03-01
00:00:00
|
210 MW | Fossil Hard coal |
| Active | LZA31-09-202406200755-001_005 |
2025-04-17
10:13:00
|
TAURON Wytwarzanie S.A. | Power plant Łaziska, Unit 9 | Planned |
2026-01-02
00:01:00
|
2026-04-12
00:00:00
|
215 MW | Fossil Hard coal |
- 1